2:12 p.m.
Hi everyone, The time is again upon us to start thinking about release planning for the next major release: GHC 8.12. In keeping with our 6-month release schedule, I propose the following schedule: * Mid-June 2020: Aim to have all major features in the tree * Late-June 2020: Cut the ghc-8.12 branch * June - August 2020: 3 alpha releases * 1 September 2020: beta release * 25 September 2020: Final 8.12.1 release So, if you have any major features which you would like to merge for 8.12, now is the time to start planning how to wrap them up in the next month or so. As always, do let me know if you think this may be problematic and we can discuss options. Cheers, - Ben